Gaza Central Water and Wastewater project (Contract 1- Buraij WWTP& Wadi Gaza CPS) with 2 years O&M.
-
Categoryمباني
-
Clientبنك الائتمان لإعادة التنمية KfW
-
Supervisorمصلحة مياه بلديات الساحل
-
Funded Byبنك الائتمان لإعادة التنمية KfW
-
RegionSOUTHERN GOVERNORATE / BURAJI
-
From - To2016-10-01 00:00:00 - 2022-08-24 00:00:00
-
Value43,455,972.00$
Design/Built WWTP with capacity of 60,000 m3/day and wadi Gaza Central PS with a capacity of 7,000 m3/h. Main works included 2 floor administration building with area of 530 m²/each,400 m² workshop building, 20,988 m² road works, 2 cylindric tanks of 45,000 m³, 1,500 m³ cylindric Gas holder building, 25,000 m³ rectangular storage tanks, 8,000 L.M, piping works & 186,377 Excavation works.