Salfeet WWTP – Design, Construction, Operation and Maintenance, with Solar PV Plant

Salfeet WWTP – Design, Construction, Operation and Maintenance, with Solar PV Plant

Key facts

Capacity
About 1,900 m³/day; 82 l/s flow to treatment
Treatment process
Imhoff tanks, trickling filters and final sedimentation
Sludge / energy
Five sludge drying beds; 248 kW solar PV plant
Population served
Designed for about 20,000 population equivalent
Scope
Design–build + 2 years O&M (FIDIC Yellow Book)

Design, construction, commissioning and two years of operation and maintenance of the Salfeet Wastewater Treatment Plant in the West Bank, with a turnkey 248 kW solar PV plant, for the Municipality of Salfeet under the KfW-funded Salfeet Sewerage Project. The plant treats about 1,900 m³/day for about 20,000 population equivalent. MACC designed, built and operated the plant, supervised by GITEC-IGIP. The employer took over the plant in February 2022.

Scope of work

  • Detailed design of the treatment plant and associated works
  • Inlet works: penstock, coarse and fine screens with screenings wash presses, aerated grit and grease chambers with grit classifier, inlet flow flume with sampler, and a faecal-sludge acceptance point
  • Two Imhoff tanks for primary sedimentation and sludge digestion
  • Two trickling filters with internal recirculation and two final sedimentation tanks
  • Five sludge drying beds and an odour-control unit
  • Operational and administration buildings, ancillary piping, mechanical equipment and electrical wiring
  • Turnkey 248 kW solar PV plant
  • 24 months of operation and maintenance with training of the municipality's operating staff, including training abroad

Technology and key components

  • Coarse screen with 10 mm openings and two fine screens with 3 mm openings
  • Two aerated grit and grease chambers, 11 m long
  • Two Imhoff tanks, 23.4 m × 7.1 m, 9.55 m inner height
  • Two trickling filters, 12.5 m diameter and 4.85 m high, with 100–200% recirculation
  • Two final sedimentation tanks, 15 m diameter
  • Five sludge drying beds, 30 m × 12 m each