Key facts
- Project
- C1 – Central Gaza WWTP (60,000 m³/day) and Wadi Gaza Central Pumping Station
- Client
- Coastal Municipalities Water Utility (CMWU)
- Funded by
- KfW
- Capacity
- 3 × 2,790 m³/h pumps (two duty, one standby)
- Milestone
- Commissioning
MACC has completed commissioning of the Wadi Gaza Central Pumping Station, which lifts wastewater to the new Central Gaza Wastewater Treatment Plant at Buriej; the operation and maintenance phase will follow.
In February 2020 MACC completed the commissioning phase of the Wadi Gaza Central Pumping Station (CPS). The station is now ready to enter its operation and maintenance phase.
The CPS was built under Contract 1 of the KfW-funded Gaza Central Wastewater Project for the Coastal Municipalities Water Utility, supervised by Dorsch International Consultants. It houses three dry-installed centrifugal pumps, two duty and one standby, each rated 2,790 m³/h at 32.8 m head and 440 kW, with mechanically raked bar screens and a septage acceptance point.
A DN1200 pressure main carries the flow from the CPS to the inlet works of the Central Gaza Wastewater Treatment Plant at Buriej, with flow measurement and a storm overflow. Commissioning of the pumping station is a key step towards bringing the 60,000 m³/day plant into service.
Related project
C1 – Central Gaza WWTP (60,000 m³/day) and Wadi Gaza Central Pumping Station
Coastal Municipalities Water Utility (CMWU) View project