Development of Tal Al Hawa, Al Zaitoon and Al Remal Al Janoobi Roads

Key facts

Pipe length
2,200 m water line; 1,000 m storm-water pipes
Area
19,800 m² asphalt paving; 22,000 m² interlocking pavers; 6,200 m kerbstones
Works
Paving, water, storm-water and sewer lines, street lighting and signs
Locations
Tal Al Hawa, Al Zaitoon and southern Al Remal, Gaza City

Road development in three Gaza City neighbourhoods, Tal Al Hawa, Al Zaitoon and southern Al Remal, for Gaza Municipality, funded by the Arab Fund for Economic and Social Development through the Islamic Development Bank. Alongside asphalt and interlocking-paver surfacing, the works renewed water, storm-water and sewer lines and added street lighting and traffic signs.

Scope of work

  • 19,800 m² of asphalt paving
  • 22,000 m² of concrete interlocking pavers
  • 6,200 m of kerbstones
  • 2,200 m of water supply line
  • 1,000 m of concrete storm-water pipes
  • 7,900 m of PVC sewer pipes
  • Street lighting and traffic signs