Key facts
- Project
- Capacity Increase of the Gaza City Seawater Desalination Plant (RO 10,000) to 12,500 m³/day (KDF-33)
- Client
- Arab and International Organization to Construct in Palestine (AIOCP)
- Funded by
- Kuwait Fund for Arab Economic Development
- Capacity
- From 10,000 to 12,500 m³/day
- Value
- US$ 1,868,948
In July 2023 MACC signed a contract to increase the capacity of the Gaza City seawater desalination plant from 10,000 to 12,500 m³/day, with Kuwait Fund financing on behalf of the Palestinian Water Authority.
In July 2023 MACC signed a new contract to increase the production capacity of the seawater desalination plant in Al-Sudaniya, North Gaza, from 10,000 to 12,500 m³/day. The contract is with the Arab and International Organization to Construct in Palestine, financed by the Kuwait Fund for Arab Economic Development on behalf of the Palestinian Water Authority.
The plant is the STLV RO 10,000 seawater reverse-osmosis plant that MACC itself built for CMWU. The new works increase the capacity of the RO trains one train at a time, so that the plant stays in operation and water supply to Gaza City continues throughout, and add a new beach well connected to the intake, rehabilitation of the RO building and the supply of spare parts.
Work started in August 2023.