Key facts
- Capacity
- From 10,000 to 12,500 m³/day
- Technology
- Seawater reverse osmosis (SWRO), existing plant
- Intake
- One new beach well
- Scope
- Capacity increase train by train inside the operating plant; RO building rehabilitation; spare parts
Capacity increase of the seawater reverse-osmosis plant in North Gaza (the STLV RO 10,000 plant MACC built) from 10,000 to 12,500 m³/day, for the Arab and International Organization to Construct in Palestine (AIOCP), with Kuwait Fund financing, on behalf of the Palestinian Water Authority. The works are planned train by train inside the operating plant so that water supply can continue. MACC signed the contract in July 2023 and started work in August 2023; the works were paused by the war in October 2023.
Scope of work
- Capacity increase of the RO trains, carried out train by train while the plant stays in operation
- A new beach well and its connection to the intake
- Rehabilitation of the RO building
- Supply of spare parts