MACC has signed Contract W01 with the Palestinian Water Authority to supply and install about 65 km of ductile-iron pipelines, DN150 to DN1600, across the Rafah and Khan Younis governorates with World Bank funding.
MACC has signed Contract W01 (PWA/WB/2021/063-CTD), Reconfiguration of Water Distribution Systems in the Southern Gaza Governorates, with the Palestinian Water Authority. The World Bank-funded contract is worth US$ 22,421,130 and is supervised by Technical Engineering Consulting Co. (TECC).
The contract is part of the Gaza Central Desalination Plant and Associated Works, Phase 1. It reconfigures the water distribution systems of the Rafah and Khan Younis governorates so that desalinated water from the planned central plant can be distributed across their municipalities.
The scope covers the supply and installation of about 65 km of ductile-iron pipelines from DN150 to DN1600, connections to the existing networks with valve chambers, reservoir upgrades including the Tal Al Sultan reservoir, and environmental and social management of the works under World Bank requirements, in nine municipalities from Rafah to Wadi Al Salqa.