Key facts
- Pipe length
- 1,600 m
- Diameters
- 400 mm, connected to the existing 315 mm line
- Pipe material
- HDPE, PN12.5 (minimum wall 37.4 mm)
- Scope
- Supply, laying and testing; 30-day completion period
Emergency construction of the pipeline that feeds the Bani Suhaila reservoir from the Mekorot supply, for the Arab and International Organization to Construct in Palestine (AIOCP), funded by the Higher Committee for Reconstruction in Palestine – Jordan. MACC supplied and laid 1,600 m of 400 mm HDPE pipe within a 30-day completion period under the contract signed on 28 March 2024.
Scope of work
- Supply and lay 1,600 m of HDPE pressure pipe, 400 mm, PN12.5 (minimum wall thickness 37.4 mm)
- Trench excavation to the required depth, backfilling and removal of surplus soil to an approved municipal site
- Butt welding and all fittings: sleeves, anchors, caps, blind flanges, tees and bends at various angles
- Concrete thrust blocks (B300)
- Relocation or level adjustment of existing utility pipes, ducts and cables crossed by the line
- Stainless-steel tracer wire and detectable warning tape
- Connection to the existing 315 mm HDPE pipe with reducers and accessories
- Pressure testing of the completed line