Rehabilitation and Maintenance of Part of the Water Network in Gaza City

  • Category
    Emergency works 2024–2026
  • Client
    Operation Chivalrous Knight 3
  • Supervisor
    Operation Chivalrous Knight 3
  • Funded By
    -
  • Region
    Gaza City
  • From - To
    2024-11-26 - 2024-12-26
  • Value
    118,100.00$

Key facts

Locations
Gaza City
Response
Emergency repair of a water network
Items / works
1,700 m of UPVC pipe, 110–225 mm, supplied from Egypt

Rehabilitation and maintenance of part of the Gaza City water network during the war, funded by Operation Chivalrous Knight 3. MACC supplied UPVC pipe from Egypt and installed 1,700 m of pipe with diameters from 110 to 225 mm.