Rehabilitation pf Sheikh Redwan stormwater Pressure Pipeline
-
CategoryEmergency
-
Clientالهيئة العربية للاعمار
-
Supervisorالهيئة العربية للاعمار
-
Funded By-
-
RegionSouthern Governorate
-
From - To2024-08-25 - 2024-11-15
-
Value349,929.00$
Extending two 630 mm diameter pressure lines made of HDPE until reaching the highest point in the street (Al-Shifa Street intersection), the distance is about 350m, constructing an energy breaker manhole at the end point. Excavating a surface drainage channel to drain water from the elevated area to the sea with a length of approximately 1200 m.