إنشاء محطة معالجة مشروع عامر
-
Categoryمحطات الضخ , التحكم عن بعد
-
Clientسلطة المياه الفلسطينية
-
Supervisorمركز الهندسة و التخطيط
-
Funded Byالبنك الدولي
-
RegionJabaliya
-
From - To2010-10-01 00:00:00 - 2013-08-01 00:00:00
-
Value1,452,323.00$
Construction of Amer Pumping Station (1200 m3/hour) at Jabaliya Municipality that covers all buildings and facilities including the bar screen, wet-dry well, supports for the pressure main inside the pump site, service building. landscaping, boundary walls generator room and associated works, fuel tanks, mechanical works. Also, the contract includes the electrical works. Installation of gravity pipe line (UPVC 630mm) form the collection manhole to the inlet manhole
The project major quantities are
1-Sewer Pipe Works 500 m
2-Earthworks 1,500 m3
3-Concrete Works 800 m3
4-Generator 400KVA