Design & Construction of Salfeet Wastewater Treatment Plant+ 2 years Operation and Maintenance Service and the Optional Item Small Photovoltaic Power Plant.
-
ClientNablus Municipalty
-
SupervisorSALFEET MUNICIPALITY
-
Funded ByKFW
-
RegionWestbank
-
From - To2017-07-11 - 2024-03-01
-
Value7,075,188.00$
Supply and Installation of plant and Equipment of North Gaza Waste Water Treatment plant/ Works completion contract.
-
ClientWorld Bank
-
SupervisorPWA
-
Funded ByWORLD BANK
-
RegionNORTHERN GOVERNORATE
-
From - To2017-11-01 - 2018-05-01
-
Value6,285,940.00$
Gaza Central Water and Wastewater project (Contract 1- Buraij WWTP& Wadi Gaza CPS) with 2 years O&M.
-
ClientKFW
-
SupervisorCMWU
-
Funded ByKFW
-
RegionSOUTHERN GOVERNORATE / BURAJI
-
From - To2016-10-01 - 2022-08-24
-
Value43,455,972.00$
Gaza Central Waste Water Treatment Plant Sheikh Ejleen WWTP- C6 Measures
-
ClientCMWU
-
SupervisorDORSCH INTERNATIONAL CONSULTANTS GMBH
-
Funded ByKFW
-
RegionGaza City
-
From - To2018-05-01 - 2019-08-01
-
Value0.00$