Supply of 144 Auto-Reclosure
Design and Construction of RO 6,000 m³/day of desalinated water, including main steel structure building with total area of 850 m² including all electro- mechanical works, 3 tanks with total capacity of 550 m³,
Design/Built,Supply & installation and 3 years O&M of 4.7 MW PV grid-tied system, distributed in two sites (ALBURIEJ 3.5 MW, SHIEKH AJLEEN 1.2 MW)+synchronization works between the PV system and the already installed two Diesel Generator at each site separately. The surplus power will be sold back to GEDCO.