MACC handed over Contract 2 (civil works) of the Gaza Central Sewerage Project in February 2012 at a final value of EUR 6,062,893, with the defects liability period running to the end of December 2013.
MACC handed over Contract 2 (civil works) of the Gaza Central Sewerage Project in February 2012 at a final value of EUR 6,062,893, with the defects liability period running to the end of December 2013.
On 7 February 2012 MACC handed over Contract 1 of the Gaza Central Sewerage Project, the supply of imported equipment and materials for the Sheikh Ajleen plant upgrade, at a final value of EUR 8,328,608.
MACC has completed all road works at the North Gaza Wastewater Treatment Plant site, finishing the internal roads that connect the treatment units, buildings and infrastructure of the NGEST project.
Construction of several buildings at the North Gaza Wastewater Treatment Plant is complete, providing the starting point for commissioning and the preparations for final handover of the NGEST works.