ER6.3 – Internal Water Network Reconfiguration

ER6.3 – Internal Water Network Reconfiguration

Key facts

Pipe length
About 7,000 m
Diameters
110, 160, 225, 315 and 450 mm; valves up to 12 inch
Pipe material
UPVC, PN 12.5

Reconfiguration of an internal water network under contract ER6.3, funded by the German Government through KfW for the Coastal Municipalities Water Utility (CMWU) and supervised by Dorsch International Consultants. MACC supplied, installed and commissioned about 7,000 m of UPVC pipes with fittings, valves and manholes, and reinstated about 6,000 m² of asphalt.

Scope of work

  • Supply, installation and commissioning of about 7,000 m of UPVC pipes, PN 12.5, from 110 to 450 mm
  • All fittings and valves, up to 12 inch
  • Manholes and valve chambers
  • Asphalt reinstatement of about 6,000 m²
  • Environmental, social, health and safety measures, certified by CMWU