Key facts
- Pipe length
- 11,450 m installed; 7,646 m supplied
- Diameters
- 110–450 mm
- Pipe material
- HDPE (SDR 11)
- Controls
- Farm-head works with automatic metering valves; bulk water meter chambers
Lot 2 of the KfW-funded Wastewater Reuse Project Nablus: a distribution system that carries treated wastewater to farms for irrigation, built for Nablus Municipality. MACC installed 11,450 m of HDPE pipelines from 110 to 450 mm with fittings and instrumentation, and supplied a further 7,646 m of pipe and 34,250 m of fencing material. A variation extended the network to serve about 2,300 dunums of farmland.
Scope of work
- Installation of 11,450 m of HDPE pipelines from 110 to 450 mm
- Mechanical fittings, valves and instrumentation, including washout and air-vent chambers
- Farm-head works with automatic metering valves for farm connections
- Bulk water meter chambers (DN100–DN300) for district metering, added under Variation 1
- Supply of 7,646 m of HDPE pipes from 110 to 250 mm, with fittings and instrumentation
- Supply of fencing material for 34,250 m