Gaza Boosters Project – GW37

  • Category
    PUMPING STATIONS, SCADA, PLC
  • Client
    PECDAR
  • Supervisor
    MUNICIPALITY OF GAZA
  • Funded By
    WORLD BANK
  • Region
    Gaza City
  • From - To
    1998-02-01 00:00:00 - 2000-01-01 00:00:00
  • Value
    1,200,000.00$

The Project included installation of electro-mechanical equipment

(screen, grill removal, pumps, valves, generator, PLC, MCC, MDB, Flow meter) with all related civil work (Chamber, service building manhole, pump bit, landscaping, piping, manifold (5000m), in addition to a full testing and Commissioning for two sewage pumping station

  • AI Fawayda PS (capacity 10,000 M3/d)
  • GAZA Booster GW37
  • Karni Sewage pump station (industrial Zone
  • Stormwater pump station for Sheikh Ejleen storm water pond