Installation of filling station at South Gaza Desalination Plant

  • Category
    Emergency
  • Client
    UNICEF
  • Supervisor
    UNICEF
  • Funded By
    -
  • Region
    Southern Governorate
  • From - To
    2024-12-25 - 2025-05-30
  • Value
    36,363.00$

Installation of a booster pump with capacity of 60m3/hr at 20 m head f

  • Installation of three overhead truck filling points using reinforced 4" filling hoses connected to 3” HDPE filling bars.
  • Laying of all piping works between pumps and filling points, including 160mm, 110mm, HDPE pipes (PN16).
  • Supply and installation of painted mild 4 steel structures for the filling units